PENERAPAN MANAJEMEN WAKTU MENGGUNAKAN NETWORK PLANNING (CPM) PADA PROYEK KONSTRUKSI JALAN (STUDI KASUS PENINGKATAN JALAN Sp. BEREMBANG – Sp. JAMBI KECIL)

Elvira Handayani, Dedy Iskandar

Abstract


One of the methods in the application of Network Planning on construction projects is the Critical Path Method (CPM).

Use of critical path method is to be able to know the the critical path of a project in which an activity can not be delayed, so that the execution time can be controlled to determine the earliest and the latest of starting time. As such factors can delay the project in minimizing

Road Improvement Works Sp. Berembang - Sp. Small Jambi has a contract value of Rp. 9,969,162,000.00 and the turnaround time is 217 calendar days. Application of CPM on the job resulted in an accelerated completion of work to 210 calendar days and 6 work items that are on the critical path. Acceleration time of completion of the work provides implementation costs Rp. 9,956,247,162.00 or additional profit of Rp. 12,914,838.00.

Keyword:  Time management, Critical path method, road construction

Full Text:

PDF


DOI: http://dx.doi.org/10.33087/jiubj.v15i1.194

Refbacks

  • There are currently no refbacks.


Creative Commons License
This work is licensed under a Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License.

ADRESS JOURNAL

JURNAL ILMIAH UNIVERSITAS BATANGHARI JAMBI (JIUBJ)
Published by Lembaga Penelitian dan Pengabdian kepada Masyarakat
Adress: Jl.Slamet Ryadi, Broni-Jambi, Kec.Telanaipura, Kodepos: 36122, email: jiubj.unbari@gmail.com, Phone: 0741-670700

Creative Commons License This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.